Activity Scheduling Problem
In this lesson, we go through a simple problem and solve it with the Greedy Approach.
We'll cover the following...
Problem Statement
Say you are given activities with their start and finish times. Select the maximum number of activities that can be performed by a single person, assuming that a person can only work on a single activity at a time.
Mathematically, Let be the set of activities that compete for a resource. Each activity has its starting time and finish time ...